Car Parts Production Inspection in Hungary and Slovakia: A Practical DUPRO Guide

A practical guide to car parts production inspection (DUPRO) at plants in Hungary and Slovakia. It explains when to book the visit, what the inspector measures on parts taken from the line, part-specific checks for die castings, machined, moulded, stamped, coated parts and wire harnesses, process and traceability checks, automotive packaging and labelling, sampling and acceptance rules, common findings and how to act on them, and which documents to prepare.

Car Parts Production Inspection in Hungary and Slovakia: A Practical DUPRO Guide
Published on: Modified on: 14 min read

A car parts production inspection, usually called a during production inspection or DUPRO, is an on-site check at the Hungarian or Slovak plant once about 10 to 20% of your order has been produced. The inspector measures parts taken straight from the line against your drawing, reviews the process records behind them and checks how finished parts are being packed and labelled. The purpose is to find a drifting dimension, a wrong component or a packing error while most of the order is still unmade.

What a During Production Inspection Covers on Car Parts

A during production inspection on automotive parts has two halves: the parts themselves and the process making them. A pre-shipment inspection tells you whether a finished lot is acceptable. A DUPRO tells you whether the lot will be acceptable if the line keeps running as it is, which is a different and more useful question when you still have 80% of the parts to come.

On the day, the inspector works through these steps:

  1. Confirms the plant address, the part number, the drawing revision and the quantity produced so far against the plant's production records.
  2. Walks the line for your part: machines, tools, work instructions, in-process checks and where finished and rejected parts go.
  3. Checks raw material, castings, purchased components and their certificates against your approved list.
  4. Takes random samples from semi-finished and finished parts and checks dimensions, appearance and function against your drawing, boundary samples and checklist.
  5. Checks packing and labelling on the parts already boxed.
  6. Reports production status, findings classified as critical, major or minor, measurements and time-stamped photos.

The format follows our during production inspection service, adapted to drawings, control plans and the packaging rules that automotive customers use.

Where Car Parts Are Made in Hungary and Slovakia

Car parts production in Hungary and Slovakia is built around the vehicle assembly plants and their supplier networks. In Hungary, the assembly plants are Audi in Győr, Mercedes-Benz in Kecskemét, Suzuki in Esztergom and BMW in Debrecen. Machining shops, die casters, plastic moulders, harness makers and electronics plants sit around them and along the motorway corridors in Western and Central Transdanubia, Pest county and the north-east around Miskolc.

In Slovakia, vehicles are built by Volkswagen in Bratislava, Stellantis in Trnava, Kia near Žilina and Jaguar Land Rover in Nitra. Most tier-1 and tier-2 suppliers are in the west and north-west of the country, along the Váh valley through Trnava, Trenčín, Považská Bystrica and Žilina, with further clusters around Nitra and in eastern Slovakia near Košice.

When you book, give the street address of the plant that actually produces and packs your parts. Many groups run several plants in both countries under one company name, and a registered office in Budapest or Bratislava is often not where your part is made. An inspector who arrives at the wrong site loses the day.

Why IATF 16949 Plants Still Need a Car Parts Production Inspection

Most automotive suppliers in Hungary and Slovakia hold an IATF 16949 or ISO 9001 certificate. A certificate shows that a quality system exists and was audited. It does not show that the parts made for you on last Tuesday's night shift match your drawing. The non-conformities inspectors find at certified plants usually come from how production is organised:

  • Components and castings from Asia. Many plants machine or assemble castings, fasteners, connectors, magnets and housings bought from China and other Asian suppliers. A change of sub-supplier between your approved PPAP samples and bulk production is a frequent root cause.
  • Agency and foreign labour. Plants in both countries rely on agency workers, many recruited from abroad. Turnover puts new operators on crimping, deburring and visual check stations, and workmanship varies by shift.
  • Production transfers. Lines moved from Western Europe take time to run in. Dimensional drift and assembly errors show up most in the first months after a transfer.
  • Shared lines. A moulding or machining cell runs several customers' parts. Wrong tool inserts, wrong programmes and mixed labels between similar variants are real risks.
  • Smaller tier-2 and tier-3 shops. Suppliers further down the chain may never see a customer audit, and their inspection reports are sometimes copied from a previous lot.

An inspection is independent when you book and pay for it and the inspection company takes no money from the supplier. The plant's own outgoing QC has a reason to release a borderline lot. That is the gap an inspection by The Inspection Company covers: European management, German QC standards and a report written for you, with no commission from the plant.

When to Book a DUPRO for Automotive Parts

The timing of a DUPRO for automotive parts depends on where the risk sits in your order. The table shows how the stages fit together.

StageWhenMain purpose
Pre-production inspectionBefore machining, casting or moulding startsMaterial certificates, castings and purchased components against the approved list
Initial production checkFirst parts off a new or changed toolDimensions and fit on the first parts before the run continues
During production inspection10 to 20% of the order producedDimensional trends, process records, packing of the first boxes
Pre-shipment inspection100% produced, at least 80% packedRandom sampling, measurements, quantity, labels
Loading inspectionDuring truck or container loadingPallet count, load securing, trailer condition, seal number

Book the DUPRO when there are enough finished parts to sample, but early enough that a correction still matters. For a long run spread over several weeks, a second visit around 40 to 50% is worth considering on safety-relevant parts. Confirm the plant's calendar before you fix the date: many automotive suppliers in the region stop for a period in summer and over Christmas, and production pushed into the days before a shutdown is where rushed work appears. Our guide to managing production timelines explains how to set milestones the inspection can verify, and the same approach works for European plants.

Most car parts leaving Hungary and Slovakia for other EU countries travel by truck. The loading check therefore usually covers a trailer and its load securing rather than a sea container.

Dimensional Checks on Parts Taken From the Line

Dimensional checks are the core of any car parts production inspection, because a part can look perfect and still miss a bore tolerance by 0.02 mm. The inspector works from your drawing and concentrates on the characteristics you mark as special or critical, plus any listed in your control plan.

Typical tools on site are calipers, micrometers, height gauges, bore gauges, go/no-go plug and ring gauges, thread gauges and a portable roughness tester. Threads are checked to the tolerance class on the drawing, for example 6H for internal and 6g for external metric threads. Where a feature can only be measured on a coordinate measuring machine (CMM), the inspector reviews the plant's CMM report for parts from your lot, checks that it carries your part number, drawing revision and date, and can ask for a part to be measured while they watch.

During production, the pattern of measurements matters more than any single value. Useful checks are:

  • Parts from the start and the end of a shift, to see tool wear or thermal drift.
  • One part from each cavity of a multi-cavity mould or die, because one worn cavity can produce all the rejects.
  • Parts from each machine if your part runs on two or more machines.
  • Values sitting close to one tolerance limit, which the report should flag even when they pass.

Fit is checked against mating parts or the plant's check fixtures if they exist. Ask the plant to have fixtures and gauges for your part available on the day, with valid calibration labels.

Checks by Part Type

The checklist for a car parts DUPRO changes with the manufacturing process. These are the points inspectors focus on for the part types most often produced in Hungary and Slovakia.

Aluminium die castings

Die castings are checked for porosity exposed on machined faces, cold shuts, cracks, flash, incomplete fill and ejector pin marks on functional surfaces. Housings that must be sealed should have leak test records for your lot, with the test pressure and reject limit stated. The inspector checks that leak-tested parts are marked and that failed parts go to a locked reject bin, not back onto the line.

Machined parts

Machined parts are checked for burrs in bores and cross-holes, chips left in blind holes, chatter marks, and surface roughness where the drawing gives an Ra value. Technical cleanliness limits, if your specification has them, are verified against the plant's residual particle test records, since that test cannot be done on the shop floor.

Injection moulded parts

Moulded parts are checked for short shots, flash, sink marks, weld lines at load points, gate remains and warpage. The inspector reads the material marking moulded into the part to ISO 11469, for example >PA66-GF30<, and compares the resin grade and batch on the material bags at the machine with your approved material. Regrind percentage should match what your specification allows.

Stamped and welded parts

Stamped parts are checked for burr height, cracks at bends and draws, springback against the check fixture and hole positions. On spot-welded and projection-welded assemblies, the inspector looks at weld position and count, expulsion and burn-through, and reviews the plant's destructive test records, such as chisel or peel tests on parts from your lot.

Wire harnesses

Wire harnesses are checked for terminal seating, connector position assurance and locks, wire colours and cross sections against the drawing, branch lengths, tape and conduit positions, and clip orientation. Crimp quality is verified through crimp height measurements with a crimp micrometer, pull-off force results and cross-section records for each applicator and terminal combination. The plant's electrical continuity test reports should cover every harness in the lot.

Coated and plated parts

Coated parts are checked for coating thickness with a magnetic induction or eddy current gauge, coverage in recesses and threads, colour, and adhesion where the specification gives a method. Corrosion resistance cannot be tested on site, so the inspector checks the coater's salt spray reports to ISO 9227 and confirms they relate to your coating system and a recent batch.

Damaged wooden crate inspection

Process, Traceability and Line Checks

Process checks during production show whether the plant will keep making good parts after the inspector leaves. On the line for your part, the inspector looks at:

  • Whether the work instruction at each station shows your part number and current drawing revision.
  • In-process inspection sheets and SPC charts for the special characteristics, and whether out-of-limit points led to any recorded action.
  • First-off and last-off approvals for each set-up.
  • Calibration labels on gauges and fixtures used for your part.
  • Error-proofing devices on the line, and whether they are switched on and checked at shift start.
  • How rejects are identified, segregated and recorded, and where rework happens.
  • Batch traceability from raw material or casting lot to the label on the finished box.

Traceability matters most on safety-relevant parts. If a problem appears later in the field, the batch number on the box label must lead back to a specific material lot, shift and machine. A plant that cannot show this chain during a DUPRO is unlikely to show it during a recall. If you received a PPAP package for the part, the inspector can compare the process on the floor with the process flow and control plan in that package; our article on the PPAP process explains what those documents contain.

Packaging and Labelling Checks for Automotive Parts

Packaging errors are some of the easiest problems to find at the DUPRO stage, because the first boxes are already filled. Checks cover:

  • Container type against your packaging specification, for example VDA small load carriers, returnable plastic trays or one-way cartons.
  • Quantity per box and per layer, and dividers that stop machined faces and threads touching.
  • VCI bags or corrosion protection oil on steel parts going into storage or long transport.
  • Labels to the format your customer uses, such as VDA 4902 or Odette, with the correct part number, quantity, batch and supplier code, and barcodes that scan.
  • Pallet height, weight, strapping and stacking rules.

A wrong label on one box can stop an assembly line at your customer, so the inspector scans barcodes on a sample of boxes rather than reading them by eye.

Sampling and Acceptance During Production

Sampling during production differs from a final inspection because the lot is incomplete. For visual and workmanship checks, the inspector applies ISO 2859-1 tables, usually general inspection level II, to the quantity actually finished on the day. Defects are classified as critical, major or minor; TIC works with the ANSI/ASQC Z1.4 methodology, which uses the same tables.

Car parts need tighter rules than consumer goods on some points. Typical settings are zero acceptance for critical defects and for any out-of-tolerance special characteristic, a fixed number of parts for full dimensional checks (for example five per cavity or per machine), and AQL 1.0 or 0.65 for major and 2.5 for minor cosmetic defects. Put your numbers in the booking so the result is a clear pass or fail. Our during production inspection checklist shows how to structure the checklist itself.

Common Findings and What You Should Do

The findings that most often come up during car parts production inspections in Hungary and Slovakia are:

  • A dimension drifting towards one tolerance limit, often from one cavity or one machine.
  • Burrs or chips in cross-holes on machined parts.
  • Castings or purchased components from a different sub-supplier than the one approved.
  • Drawing revision on the work instruction older than the one on the order.
  • Gauges with expired calibration labels.
  • Rejects stored next to good parts without clear identification.
  • Wrong quantity per box, missing VCI protection or labels with the wrong batch number.

When the report shows a problem, act on it while the line is running:

  1. Ask the plant to stop shipping and to contain the affected parts, including those already boxed.
  2. Request a corrective action with root cause, for example an 8D report, and a date for the fix.
  3. Ask for sorting of parts produced before the fix, or book a sorting service if you do not trust the plant's own sorting.
  4. Book a re-inspection or move the pre-shipment inspection forward to confirm the fix worked on new production.
  5. Hold the balance payment or shipment release until the follow-up check passes.

Documents to Prepare Before the Inspection

The inspector can only judge your parts against what you send. Before the visit, provide:

  • The drawing at the current revision, with special and critical characteristics marked.
  • The control plan, or at least the list of characteristics to measure and the gauges to use.
  • Approved samples or boundary samples for appearance, and photos if samples cannot be sent.
  • The approved list of materials, castings and purchased components with their suppliers.
  • Your packaging and labelling specification.
  • Order quantity, production schedule and the full plant address with a contact person.
  • Your acceptance criteria: AQL levels, sample sizes for dimensional checks and what counts as critical.

With these in hand, a report from The Inspection Company arrives within 24 hours of the visit, with measurements, findings by severity and time-stamped photos. Geo-tracking records when and where the inspector checked in and out, so you can confirm the visit took place at the right plant.

If you have car parts running at a plant in Hungary or Slovakia, send us your drawing, control plan and production schedule and we will propose a during production inspection plan with sample sizes and acceptance criteria for your order. Request a free quote for your car parts inspection.

Frequently Asked Questions

When should a during production inspection be done on car parts?

Book it when about 10 to 20% of the order is produced, so there are enough parts to sample and most of the order can still be corrected. On long or safety-relevant runs, a second visit around 40 to 50% is common.

Does an IATF 16949 certificate make a DUPRO unnecessary?

No. The certificate confirms a quality system exists. A DUPRO checks whether your specific parts, made on a specific shift with specific materials, match your drawing.

Can the inspector measure features that need a CMM?

The inspector cannot carry a CMM, but reviews the plant's CMM reports for parts from your lot, checks part number, revision and date, and can ask for a part to be measured on the plant's CMM while watching.

What is the difference between a DUPRO and a PPAP?

A PPAP is the supplier's documented proof, before series production, that its process can make your part. A DUPRO is an independent check during series production that parts and process still match what was approved.

How many parts are checked during a car parts DUPRO?

Visual checks follow ISO 2859-1, usually level II, based on the quantity finished on the day. Full dimensional checks use a fixed number of parts, such as five per cavity or per machine, as set in your booking.

What happens if the DUPRO finds a critical defect?

The result is a fail. You should ask the plant to contain affected parts, provide a corrective action, sort what was already produced, and then book a follow-up inspection before releasing shipment or payment.

Quality. Trust. Assurance.

Optimize Your Quality Control Management

Leverage our instant AQL tools, or connect with TIC's experts in Asia for tailored inspection and audit solutions.

Explore our services
Your Trusted Partner in Third-Party Inspection Services Across Asia
Share this post:

Related Posts